– footbridge clearance: approx. 78 m– usable width: 5.0 m
– total width of the platform: 7.11 m– facility span: 24.0 + 50.0 + 94.0 + 50.0 + 32.0 = 250.0 m
– supporting structure: beam structure, steel lattice structure, welded from pipes;
– massive concrete supports, intermediate foundation on piles;
Development of complete technical documentation along with attainment of administrative decisions in the scope of:
– Construction of pedestrian footbridge
– Construction of the road system with access roads
– Construction of a rainwater sewage system and an absorption-retention reservoir
– Development of an environmental impact report-Drafting of geotechnical opinions, documentation of subsoil research