DESIGN
DESIGN DOCUMENTATION OF OA-2 AND OA-4 BRIDGES IN REPUBLIC OF CAMEROON
Construction work on the Olama – Kribi road (N22). LOT 1: Olama – Bingambo
Location
Republic of Cameroon
Purchaser
Republic of Cameroon. Ministry of Public Works
The Contractor
SOGEA SATOM (VINCI)
Lead design office
WSP France | subcontractor Geokonstrukcja sp z o.o.
Date of implementation
Studies: 2018-2020; Works: 2019-2020
Builiding characteristics
OA-02 The total length of the object: 35.40 m The total width of the object: 11.00 m Obstacle type: river Theoretical span of the superstructures: 22.90 m Static scheme: span slow-supported beams system Type of superstructure: prefabricated beams Foundation: reinforcement ground OA-04 The total length of the object: 32.40 m The total width of the object: 11.00 m Obstacle type: river Theoretical span of the superstructures: 14.00 m Static scheme: span slow-supported beams system Type of superstructure: prefabricated beams Foundation: reinforcement ground
Parameters
Scope of work

Preparation of design documentation in the scope of detailed design with elements of static calculations