TRENCHLESS TECHNOLOGIES
BYPASS OF MIĘKINA
Construction of the WK-1 railway bridge using the ramming method as part of the task: Connection of the bridge over the Odra River in the city of Brzeg Dolny with the national road No. 94 and the province road No. 340
Location
Miękina, Poland
Purchaser
DSDiK Wrocław
The Contractor
Mota-Engil Central Europe S.A. | Himmel & Papesch sp. z o.o.
Lead design office
Date of implementation
2017-2018
Builiding characteristics
Closed monolithic single-span reinforced concrete frame. Total length 10.80m. Usable height 5.60m.Usable width 12.60m. Direct foundation. Obstacle: embankment of a double-track railway line
Parameters
Scope of work

– Development of an executive and technological design

– Fabrication and disassembly of receiving and transmitting chambers

– Execution of the relief structure

– Execution of ramming works on the reinforced concrete frame of the underground passage with maintenance of railway traffic

– Execution of transition zones on access to the facility